Maple Harvest Wind — Project Summary

Queue ID
NYISO-C24-079
Capacity
162 MW
Technology
Wind
Status
active
Location
Onondaga, NY
Region
NYISO
Developer
Maple Harvest Wind
IA Status

Maple Harvest Wind

BetaActiveWindNYISOLBNL + Live

162 MW generation in Onondaga, NY · In queue since August 2024 · Proposed COD December 2028

162 MW

Capacity

1

Components

Wind

1y 7m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 4m

Pre-Study0%
Queue EntryAug 8, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-01

Project Details

State

NY

County

Onondaga

Region

NYISO

Developer

Maple Harvest Wind

Utility

NM-NG

Entity

NYISO

Point of Interconnection

Tilden-Cortland Line 18.

Data Source

LBNL + Live