Maple Harvest Wind
BetaActiveWindNYISOLBNL + Live
162 MW generation in Onondaga, NY · In queue since August 2024 · Proposed COD December 2028
162 MW
Capacity
1
Components
Wind
1y 7m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 4m
Pre-Study0%
Queue EntryAug 8, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-01
Project Details
State
NY
County
Onondaga
Region
NYISO
Developer
Maple Harvest Wind
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Tilden-Cortland Line 18.
Data Source
LBNL + Live