Springbrooke — Project Summary

Queue ID
NYISO-C24-076
Capacity
82.8 MW
Technology
Solar
Status
active
Location
Genesee, NY
Region
NYISO
Developer
SUNXI LLC
IA Status

Springbrooke

BetaActiveSolarNYISOLBNL

82.8 MW generation in Genesee, NY · In queue since August 2024 · Proposed COD December 2029

82.8 MW

Capacity

1

Components

Solar

1y 7m

In Queue

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

5y 4m

Pre-Study0%
Queue EntryAug 5, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-12-01

Project Details

State

NY

County

Genesee

Region

NYISO

Developer

SUNXI LLC

Utility

NM-NG

Entity

NYISO

Point of Interconnection

Southeast Batavia-Golah Line 119

Data Source

LBNL

No news available for this project.