Oyster shore Energy storage — Project Summary

Queue ID
NYISO-C24-075
Capacity
275 MW
Technology
Battery
Status
active
Location
Nassau, NY
Region
NYISO
Developer
Shore Rd ESS LLC
IA Status

Oyster shore Energy storage

BetaActiveBatteryNYISOLBNL

275 MW storage in Nassau, NY · In queue since August 2024 · Proposed COD December 2027

275 MW

Capacity

1

Components

Battery

1y 7m

In Queue

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 4m

Pre-Study0%
Queue EntryAug 2, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-01

Project Details

State

NY

County

Nassau

Region

NYISO

Developer

Shore Rd ESS LLC

Utility

LIPA

Entity

NYISO

Point of Interconnection

Shore Road 138 kV

Data Source

LBNL

No news available for this project.