Queue ID
NYISO-C24-071
Capacity
125 MW
Technology
Battery
Status
active
Location
Suffolk, NY
Region
NYISO
Developer
Sweetwaters Energy Center LLC
IA Status

Sweetwaters Energy Center

BetaActiveBatteryNYISOLBNL

125 MW storage in Suffolk, NY · In queue since August 2024 · Proposed COD May 2028

125 MW

Capacity

1

Components

Battery

1y 7m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 9m

Pre-Study0%
Queue EntryAug 1, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-05-01

Project Details

State

NY

County

Suffolk

Region

NYISO

Developer

Sweetwaters Energy Center LLC

Utility

LIPA

Entity

NYISO

Point of Interconnection

Kings Substation at 138kV open bay

Data Source

LBNL