Gala Grove BESS
BetaActiveBatteryNYISOLBNL
125 MW storage in Suffolk, NY · In queue since August 2024 · Proposed COD June 2029
125 MW
Capacity
1
Components
Battery
1y 7m
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 10m
Pre-Study0%
Queue EntryAug 1, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-06-01
Project Details
State
NY
County
Suffolk
Region
NYISO
Developer
Empire Reserve Energy, LLC
Utility
LIPA
Entity
NYISO
Point of Interconnection
Wildwood - Riverhead 138 kV
Data Source
LBNL