Hemlock Hollow Wind — Project Summary

Queue ID
NYISO-C24-052-001
Capacity
95 MW
Technology
Wind
Status
active
Location
Cattaraugus, NY
Region
NYISO
Developer
Liberty Renewables Inc.
IA Status

Hemlock Hollow Wind

BetaActiveWindNYISOLBNL + Live

95 MW generation in Cattaraugus, NY · In queue since August 2024 · Proposed COD September 2029

95 MW

Capacity

1

Components

Wind

1y 7m

In Queue

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

5y 1m

Pre-Study0%
Queue EntryAug 1, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-09-01

Project Details

State

NY

County

Cattaraugus

Region

NYISO

Developer

Liberty Renewables Inc.

Utility

NM-NG

Entity

NYISO

Point of Interconnection

Dugan - Homer Hill 115kV, Line #155

Data Source

LBNL + Live