95 MW generation in Cattaraugus, NY · In queue since August 2024 · Proposed COD September 2029
95 MW
Capacity
1
Components
Wind
1y 7m
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
5y 1m
Pre-Study0%
Queue EntryAug 1, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-09-01
Project Details
State
NY
County
Cattaraugus
Region
NYISO
Developer
Liberty Renewables Inc.
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Dugan - Homer Hill 115kV, Line #155
Data Source
LBNL + Live