Grateful Storage, LLC — Project Summary

Queue ID
NYISO-C24-050
Capacity
250 MW
Technology
Battery
Status
active
Location
Orange, NY
Region
NYISO
Developer
Grateful Storage, LLC
IA Status

Grateful Storage, LLC

BetaActiveBatteryNYISOLBNL

250 MW storage in Orange, NY · In queue since August 2024 · Proposed COD May 2030

250 MW

Capacity

1

Components

Battery

1y 7m

In Queue

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

5y 9m

Pre-Study0%
Queue EntryAug 1, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-05-01

Project Details

State

NY

County

Orange

Region

NYISO

Developer

Grateful Storage, LLC

Utility

CHGE

Entity

NYISO

Point of Interconnection

Rock Tavern - Roseton 345 kV

Data Source

LBNL

No news available for this project.