North Catskill DG LLC
BetaActiveBatteryNYISOLBNL
100 MW storage in Greene, NY · In queue since August 2024 · Proposed COD May 2028
100 MW
Capacity
1
Components
Battery
1y 7m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 9m
Pre-Study0%
Queue EntryAug 1, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-05-01
Project Details
State
NY
County
Greene
Region
NYISO
Developer
BayWa r.e Solar Projects LLC
Utility
CHGE
Entity
NYISO
Point of Interconnection
North Catskill -Churchtown 115 kV
Data Source
LBNL
No news available for this project.