BPP NY Lansing BESS I
BetaActiveBatteryNYISOLBNL + Live
200 MW storage in Tompkins, NY · In queue since August 2024 · Proposed COD December 2026
200 MW
Capacity
1
Components
Battery
1y 7m
In Queue
—
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 4m
Pre-Study0%
Queue EntryAug 1, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-01
Project Details
State
NY
County
Tompkins
Region
NYISO
Developer
BPP NY Lansing BESS I LLC
Utility
NYSEG
Entity
NYISO
Point of Interconnection
Milliken 115kV (aka Cayuga 115kV)
Data Source
LBNL + Live
No news available for this project.