Lincoln Park DG, LLC — Project Summary

Queue ID
NYISO-C24-047
Capacity
150 MW
Technology
Battery
Status
active
Location
Ulster, NY
Region
NYISO
Developer
BayWa r.e. Solar Projects LLC
IA Status

Lincoln Park DG, LLC

BetaActiveBatteryNYISOLBNL + Live

150 MW storage in Ulster, NY · In queue since August 2024 · Proposed COD May 2028

150 MW

Capacity

1

Components

Battery

1y 7m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 9m

Pre-Study0%
Queue EntryAug 1, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-05-01

Project Details

State

NY

County

Ulster

Region

NYISO

Developer

BayWa r.e. Solar Projects LLC

Utility

CHGE

Entity

NYISO

Point of Interconnection

Lincoln Park - East Kingston 115 kV

Data Source

LBNL + Live