Robinson Hill BESS — Project Summary

Queue ID
NYISO-C24-046
Capacity
1117 MW
Technology
Battery
Status
active
Location
Broome, NY
Region
NYISO
Developer
Oakdale BESS
IA Status

Robinson Hill BESS

BetaActiveBatteryNYISOLBNL

1,117 MW storage in Broome, NY · In queue since August 2024 · Proposed COD October 2027

1,117 MW

Capacity

1

Components

Battery

1y 7m

In Queue

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 2m

Pre-Study0%
Queue EntryAug 1, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-10-01

Project Details

State

NY

County

Broome

Region

NYISO

Developer

Oakdale BESS

Utility

NYSEG

Entity

NYISO

Point of Interconnection

Oakdale 345kv Substation

Data Source

LBNL

No news available for this project.