Honey Bee Battery Storage, LLC — Project Summary

Queue ID
NYISO-C24-044
Capacity
199 MW
Technology
Battery
Status
active
Location
Rensselaer, NY
Region
NYISO
Developer
BayWa r.e Solar Projects LLC
IA Status

Honey Bee Battery Storage, LLC

BetaActiveBatteryNYISOLBNL

199 MW storage in Rensselaer, NY · In queue since August 2024 · Proposed COD May 2028

199 MW

Capacity

1

Components

Battery

1y 7m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 9m

Pre-Study0%
Queue EntryAug 1, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-05-01

Project Details

State

NY

County

Rensselaer

Region

NYISO

Developer

BayWa r.e Solar Projects LLC

Utility

NM-NG

Entity

NYISO

Point of Interconnection

North Troy -Hoosick Line 5 115 kV

Data Source

LBNL