Hoffman Falls Wind 2
BetaActiveWindNYISOLBNL + Live
29.8 MW generation in Madison, NY · In queue since August 2024 · Proposed COD December 2027
29.8 MW
Capacity
1
Components
Wind
1y 7m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 4m
Pre-Study0%
Queue EntryAug 1, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Project Details
State
NY
County
Madison
Region
NYISO
Developer
Liberty Renewables Inc.
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Fenner - Shippy Rd Line 3 115 kV
Data Source
LBNL + Live