Gunns Corners Solar
BetaActiveSolarNYISOLBNL
140 MW generation in Jefferson, NY · In queue since August 2024 · Proposed COD December 2027
140 MW
Capacity
1
Components
Solar
1y 7m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 4m
Pre-Study0%
Queue EntryAug 1, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Project Details
State
NY
County
Jefferson
Region
NYISO
Developer
Northland Power U.S. Projects Inc
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Thousand Islands-Coffeen Line 4: Lyme Tap 115kV
Data Source
LBNL
No news available for this project.