Bull Run Solar — Project Summary

Queue ID
NYISO-C24-029
Capacity
100 MW
Technology
Solar
Status
active
Location
Clinton, NY
Region
NYISO
Developer
Bull Run Solar LLC
IA Status

Bull Run Solar

BetaActiveSolarNYISOLBNL

100 MW generation in Clinton, NY · In queue since August 2024 · Proposed COD December 2030

100 MW

Capacity

1

Components

Solar

1y 7m

In Queue

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

6y 4m

Pre-Study0%
Queue EntryAug 1, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-12-01

Project Details

State

NY

County

Clinton

Region

NYISO

Developer

Bull Run Solar LLC

Utility

NYPA

Entity

NYISO

Point of Interconnection

230 kV Ellenburg Substation

Data Source

LBNL

No news available for this project.