Bull Run Solar
BetaActiveSolarNYISOLBNL
100 MW generation in Clinton, NY · In queue since August 2024 · Proposed COD December 2030
100 MW
Capacity
1
Components
Solar
1y 7m
In Queue
—
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
6y 4m
Pre-Study0%
Queue EntryAug 1, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-12-01
Project Details
State
NY
County
Clinton
Region
NYISO
Developer
Bull Run Solar LLC
Utility
NYPA
Entity
NYISO
Point of Interconnection
230 kV Ellenburg Substation
Data Source
LBNL
No news available for this project.