COSW BCEH
BetaActiveOffshore WindNYISOLBNL
1,310 MW generation in Kings, NY · In queue since August 2024 · Proposed COD December 2031
1,310 MW
Capacity
1
Components
Offshore Wind
1y 7m
In Queue
—
IA Status
COD target: 2031
Interconnection Timeline
Total Duration
7y 4m
Pre-Study0%
Queue EntryAug 1, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2031-12-01
Project Details
State
NY
County
Kings
Region
NYISO
Developer
Community Offshore Wind, LLC
Utility
ConEd
Entity
NYISO
Point of Interconnection
Brooklyn Clean Energy Hub 345 kV
Data Source
LBNL