Salt Rush Wind Energy
BetaActiveWindNYISOLBNL
150 MW generation in Wyoming, NY · In queue since August 2024 · Proposed COD November 2029
150 MW
Capacity
1
Components
Wind
1y 7m
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
5y 3m
Pre-Study0%
Queue EntryAug 1, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-11-01
Project Details
State
NY
County
Wyoming
Region
NYISO
Developer
Salt Rush Wind Energy LLC
Utility
NYSEG
Entity
NYISO
Point of Interconnection
Stony Creek 230 kV
Data Source
LBNL
No news available for this project.