Seventy Seven Project
BetaActiveSolarNYISOLBNL
100 MW generation in Wyoming, NY · In queue since August 2024 · Proposed COD May 2030
100 MW
Capacity
1
Components
Solar
1y 7m
In Queue
—
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
5y 9m
Pre-Study0%
Queue EntryAug 1, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-05-01
Project Details
State
NY
County
Wyoming
Region
NYISO
Developer
Good Ole 77 Energy LLC
Utility
NYSEG
Entity
NYISO
Point of Interconnection
High Sheldon 230 kV
Data Source
LBNL