Roma Storage — Project Summary

Queue ID
NYISO-C24-014
Capacity
150 MW
Technology
Battery
Status
active
Location
Queens, NY
Region
NYISO
Developer
Roma Storage
IA Status

Roma Storage

BetaActiveBatteryNYISOLBNL

150 MW storage in Queens, NY · In queue since August 2024 · Proposed COD August 2028

150 MW

Capacity

1

Components

Battery

1y 7m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4 years

Pre-Study0%
Queue EntryAug 1, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-08-01

Project Details

State

NY

County

Queens

Region

NYISO

Developer

Roma Storage

Utility

ConEd

Entity

NYISO

Point of Interconnection

Astoria East 138 kV

Data Source

LBNL