EI Melville — Project Summary

Queue ID
NYISO-C24-012
Capacity
1240 MW
Technology
Offshore Wind
Status
active
Location
NY
Region
NYISO
Developer
Empire Wind 2 LLC
IA Status

EI Melville

BetaActiveOffshore WindNYISOLBNL

1,240 MW generation in NY · In queue since August 2024 · Proposed COD December 2033

1,240 MW

Capacity

1

Components

Offshore Wind

1y 7m

In Queue

IA Status

COD target: 2033

Interconnection Timeline

Total Duration

9y 4m

Pre-Study0%
Queue EntryAug 1, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2033-12-01

Project Details

State

NY

County

Region

NYISO

Developer

Empire Wind 2 LLC

Utility

NYPA

Entity

NYISO

Point of Interconnection

Ruland Road 345 kV

Data Source

LBNL

No news available for this project.