KCE NY 21
60 MW storage in Suffolk, NY · In queue since August 2024 · Proposed COD January 2028
60 MW
Capacity
1
Components
Battery
1y 7m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 5m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-01-01
State
NY
County
Suffolk
Region
NYISO
Developer
KCE NY 21, LLC
Utility
LIPA
Entity
NYISO
Point of Interconnection
Pulaski 69kV Substation
Data Source
LBNL + Live
Key Capture Energy completes ITC transfer and construction on two 100MW Texas BESS projects
US battery storage developer Key Capture Energy (KCE) has begun commercial operations for two 100MW battery energy storage system (BESS) projects in Texas.
Key Capture Energy completes ITC transfer and construction on two 100MW Texas BESS projects
US battery storage developer Key Capture Energy (KCE) has begun commercial operations for two 100MW battery energy storage system (BESS) projects in Texas.
Key Capture Energy completes ITC transfer and construction on two 100MW Texas BESS projects
US battery storage developer Key Capture Energy (KCE) has begun commercial operations for two 100MW battery energy storage system (BESS) projects in Texas.
Key Capture Energy completes ITC transfer and construction on two 100MW Texas BESS projects
US battery storage developer Key Capture Energy (KCE) has begun commercial operations for two 100MW battery energy storage system (BESS) projects in Texas.
Last updated 2026-03-26