Palladium Storage — Project Summary

Queue ID
NYISO-C24-004
Capacity
140 MW
Technology
Battery
Status
active
Location
Bronx, NY
Region
NYISO
Developer
Palladium Storage LLC
IA Status

Palladium Storage

BetaActiveBatteryNYISOLBNL + Live

140 MW storage in Bronx, NY · In queue since August 2024 · Proposed COD August 2028

140 MW

Capacity

1

Components

Battery

1y 7m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4 years

Pre-Study0%
Queue EntryAug 1, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-08-01

Project Details

State

NY

County

Bronx

Region

NYISO

Developer

Palladium Storage LLC

Utility

NYPA

Entity

NYISO

Point of Interconnection

Hell Gate Annex 138KV Substation

Data Source

LBNL + Live

No news available for this project.