Alabama Solar Park LLC — Project Summary

Queue ID
NYISO-995
Capacity
130 MW
Technology
Solar
Status
active
Location
Genesee, NY
Region
NYISO
Developer
Alabama Solar Park LLC
IA Status

Alabama Solar Park LLC

BetaActiveSolarNYISOLBNL

130 MW generation in Genesee, NY · In queue since February 2020 · Proposed COD October 2028

130 MW

Capacity

1

Components

Solar

6y 1m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

8y 8m

Pre-Study0%
Queue EntryFeb 27, 2020

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-10-01

Project Details

State

NY

County

Genesee

Region

NYISO

Developer

Alabama Solar Park LLC

Utility

NM-NG

Entity

NYISO

Point of Interconnection

Lockport - Batavia 115kV (Line#112)

Data Source

LBNL