East Setauket Energy Storage
BetaActiveBatteryNYISOLBNL
125 MW storage in Suffolk, NY · In queue since January 2020 · Proposed COD April 2027
125 MW
Capacity
1
Components
Battery
6y 2m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
7y 3m
Pre-Study0%
Queue EntryJan 10, 2020
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-04-01
Project Details
State
NY
County
Suffolk
Region
NYISO
Developer
Savion, LLC
Utility
LIPA
Entity
NYISO
Point of Interconnection
Holbrook - Miller Place 138kV
Data Source
LBNL