Sugar Maple Solar
BetaActiveSolarNYISOLBNL
125 MW generation in Lewis, NY · In queue since December 2019 · Proposed COD December 2027
125 MW
Capacity
1
Components
Solar
6y 3m
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
8 years
Impact Study25%
Queue EntryDec 5, 2019
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Project Details
State
NY
County
Lewis
Region
NYISO
Developer
Sugar Maple Solar, LLC
Utility
NM-NG
Entity
NYISO
Point of Interconnection
North Carthage - Taylorville #8 and Black River - Taylorville #2 115kV
Data Source
LBNL
No news available for this project.