Astoria Energy Storage
BetaActiveBatteryNYISOLBNL
100 MW storage in Queens, NY · In queue since October 2019 · Proposed COD March 2026
100 MW
Capacity
1
Components
Battery
6y 5m
In Queue
System Impact Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
6y 5m
Schedule
1 months past proposed COD
Impact Study25%
Queue EntryOct 28, 2019
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-03-01
Project Details
State
NY
County
Queens
Region
NYISO
Developer
East River ESS, LLC
Utility
ConEd
Entity
NYISO
Point of Interconnection
Astoria West 138kV
Data Source
LBNL