Garnet Energy Center
BetaActiveSolarNYISOLBNL
200 MW generation in Cayuga, NY · In queue since June 2019 · Proposed COD November 2025
200 MW
Capacity
1
Components
Solar
6y 9m
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
6y 5m
Schedule
5 months past proposed COD
Facilities Study50%
Queue EntryJun 11, 2019
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-11-01
Project Details
State
NY
County
Cayuga
Region
NYISO
Developer
Garnet Energy Center, LLC
Utility
NYPA
Entity
NYISO
Point of Interconnection
Pannell - Clay 345kV
Data Source
LBNL
No news available for this project.