100 MW generation in Franklin, NY · In queue since June 2019 · Proposed COD June 2027
100 MW
Capacity
1
Components
Solar
6y 9m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
8 years
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
State
NY
County
Franklin
Region
NYISO
Developer
Brookside Solar, LLC
Utility
NYSEG
Entity
NYISO
Point of Interconnection
Chateaugay - Willis 115kV
Data Source
LBNL
Virtual public hearing set for Franklin County solar farm
The New York State Public Service Commission will hold a virtual public statement hearing on Tuesday, Nov. 19 concerning a petition filed in...
NY regulators give greenlight to Franklin County solar project
New York's State Office of Renewable Energy Siting gave the go-ahead to Brookside Solar for the 1000-acre solar farm located on the border...
NY regulators give greenlight to Franklin County solar project
New York's State Office of Renewable Energy Siting gave the go-ahead to Brookside Solar for the 1000-acre solar farm located on the border...
100-megawatt solar project in Chateaugay, Burke moves forward
CHATEAUGAY — A 100-megawatt solar energy project may soon move forward in Chateaugay and Burke after the Office of Renewable Energy Siting...