Brookside Solar — Project Summary

Queue ID
NYISO-880
Capacity
100 MW
Technology
Solar
Status
active
Location
Franklin, NY
Region
NYISO
Developer
Brookside Solar, LLC
IA Status
System Impact Study

Brookside Solar

BetaActiveSolarNYISOLBNL

100 MW generation in Franklin, NY · In queue since June 2019 · Proposed COD June 2027

100 MW

Capacity

1

Components

Solar

6y 9m

In Queue

System Impact Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

8 years

Impact Study25%
Queue EntryJun 10, 2019

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-06-01

Project Details

State

NY

County

Franklin

Region

NYISO

Developer

Brookside Solar, LLC

Utility

NYSEG

Entity

NYISO

Point of Interconnection

Chateaugay - Willis 115kV

Data Source

LBNL