Queue ID
NYISO-848
Capacity
20 MW
Technology
Solar
Status
active
Location
St. Lawrence, NY
Region
NYISO
Developer
SunEast Fairway Solar LLC
IA Status
Facility Study

Fairway Solar

BetaActiveSolarNYISOLBNL

20 MW generation in St. Lawrence, NY · In queue since May 2019 · Proposed COD March 2025

20 MW

Capacity

1

Components

Solar

6y 10m

In Queue

Facility Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

5y 10m

Schedule

13 months past proposed COD

Facilities Study50%
Queue EntryMay 20, 2019

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-03-01

Project Details

State

NY

County

St. Lawrence

Region

NYISO

Developer

SunEast Fairway Solar LLC

Utility

NM-NG

Entity

NYISO

Point of Interconnection

McIntyre - Corning 115kV (Line#6)

Data Source

LBNL