Valley Solar
20 MW generation in Tioga, NY · In queue since April 2019 · Proposed COD November 2024
20 MW
Capacity
1
Components
Solar
6y 11m
In Queue
Facility Study
IA Status
COD target: 2024
Total Duration
5y 7m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-11-01
State
NY
County
Tioga
Region
NYISO
Developer
SunEast Valley Solar LLC
Utility
NYSEG
Entity
NYISO
Point of Interconnection
Owego 34.5kV Substation
Data Source
LBNL
Spud Valley solar project on track to build in Alamosa County
Photo of NextEra's 250 MW Thunder Wolf Energy Center project in Pueblo, which is similar to the 200 MW proposed Spud Valley Energy Center...
A proposed Willamette Valley solar park is still in the mix. Neighbors want to nix it
Neighbors hoped the sun was setting on the planned Muddy Creek solar park. Now it seems the company behind it is preparing for a new dawn.
Hollister Fire contract for Panoche Valley Solar Farm OK’d
Lea este artículo en español aquí. Following an increase in fire incidents at the Panoche Valley Solar Farm requiring extra resources such...
Pleasant Valley Solar 2 financing clears way for data centers and high-tech manufacturing in Idaho
Utah-based developer rPlus Energies' securing of $100 million in tax equity funding from Truist Bank for its Pleasant Valley Solar 2 project...
Last updated 2026-03-26