Arthur Kill Energy Storage 1
BetaActiveBatteryNYISOLBNL
15 MW storage in Richmond, NY · In queue since April 2019 · Proposed COD September 2025
15 MW
Capacity
1
Components
Battery
6y 11m
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
6y 5m
Schedule
7 months past proposed COD
Facilities Study50%
Queue EntryApr 22, 2019
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-09-01
Project Details
State
NY
County
Richmond
Region
NYISO
Developer
GB Arthur Kill Storage LLC
Utility
ConEd
Entity
NYISO
Point of Interconnection
Fresh Kills 13.8kV
Data Source
LBNL