Bayonne Energy Center III — Project Summary

Queue ID
NYISO-815
Capacity
49.8 MW
Technology
Battery
Status
active
Location
Kings, NY
Region
NYISO
Developer
Bayonne Energy Center
IA Status
System Impact Study

Bayonne Energy Center III

BetaActiveBatteryNYISOLBNL

49.8 MW storage in Kings, NY · In queue since April 2019 · Proposed COD September 2026

49.8 MW

Capacity

1

Components

Battery

6y 11m

In Queue

System Impact Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

7y 5m

Impact Study25%
Queue EntryApr 5, 2019

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-09-01

Project Details

State

NY

County

Kings

Region

NYISO

Developer

Bayonne Energy Center

Utility

ConEd

Entity

NYISO

Point of Interconnection

Gowanus 345kV

Data Source

LBNL