Prattsburgh Wind Farm
147 MW generation in Steuben, NY · In queue since February 2019 · Proposed COD December 2025
147 MW
Capacity
1
Components
Wind
7y 1m
In Queue
System Impact Study
IA Status
COD target: 2025
Total Duration
6y 10m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-01
State
NY
County
Steuben
Region
NYISO
Developer
Prattsburgh Wind, LLC
Utility
NYSEG
Entity
NYISO
Point of Interconnection
Stoney Ridge - Canadaigua 230kV
Data Source
LBNL
PUBLIC NOTICE: Prattsburgh Wind, LLC’s pre-construction notice
This notice announces that, on or about June 8, 2025, Prattsburgh Wind, LLC (Prattsburgh or Permit Holder) will begin construction of a temporary laydown yard.
PUBLIC NOTICE: Prattsburgh Wind, LLC’s pre-construction notice
This notice announces that, on or about June 8, 2025, Prattsburgh Wind, LLC (Prattsburgh or Permit Holder) will begin construction of a temporary laydown yard.
State Approves Erecting 36 Wind Turbines in Steuben County
The New York State Office of Renewable Energy Siting and Electric Transmission has issued a final siting permit for the Prattsburgh Wind LLC...
More wind turbines planned in Steuben County receive state approval. Here's where.
A Steuben County wind farm has received final siting permits from the state Office of Renewable Energy Siting and Electric Transmission,...
Last updated 2026-03-26