Levy Grid, LLC
150 MW storage in Erie, NY · In queue since December 2018 · Proposed COD August 2025
150 MW
Capacity
1
Components
Battery
7y 3m
In Queue
System Impact Study
IA Status
COD target: 2025
Total Duration
6y 8m
Schedule
8 months past proposed COD
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-08-01
State
NY
County
Erie
Region
NYISO
Developer
Levy Grid, LLC
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Gardenville Subsation 115kV
Data Source
LBNL
Exus Renewables Secures $312 Million Financing for 140 MW Solar and Battery Storage Project in New Mexico
Discover Exus Renewables' innovative solar energy project in New Mexico, leveraging cutting-edge technology and battery storage.
Exus Renewables Secures $312 Million Financing for 140 MW Solar and Battery Storage Project in New Mexico
Discover Exus Renewables' innovative solar energy project in New Mexico, leveraging cutting-edge technology and battery storage.
Capstone, Eurowind JV seeks approval for 3.2GWh long-duration BESS in California
Canada's Capstone Infrastructure and Denmark's Eurowind Energy are proposing to construct a 400MW/3200MWh standalone BESS in Alameda County, California.
Last updated 2026-03-26