South Ripley Solar and BESS — Project Summary

Queue ID
NYISO-783
Capacity
270 MW
Technology
Solar+Battery
Status
active
Location
Chautauqua, NY
Region
NYISO
Developer
ConnectGen Chautauqua County LLC
IA Status
Facility Study

South Ripley Solar and BESS

BetaActiveSolarBatteryNYISOLBNL

270 MW hybrid in Chautauqua, NY · In queue since December 2018 · Proposed COD January 2027

270 MW

Capacity

1

Components

Solar

7y 3m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

8y 1m

Facilities Study50%
Queue EntryDec 7, 2018

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-01-01

Project Details

State

NY

County

Chautauqua

Region

NYISO

Developer

ConnectGen Chautauqua County LLC

Utility

NM-NG

Entity

NYISO

Point of Interconnection

South Ripley Substation 230kV

Data Source

LBNL

No news available for this project.