South Ripley Solar and BESS
BetaActiveSolarBatteryNYISOLBNL
270 MW hybrid in Chautauqua, NY · In queue since December 2018 · Proposed COD January 2027
270 MW
Capacity
1
Components
Solar
7y 3m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
8y 1m
Facilities Study50%
Queue EntryDec 7, 2018
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-01-01
Project Details
State
NY
County
Chautauqua
Region
NYISO
Developer
ConnectGen Chautauqua County LLC
Utility
NM-NG
Entity
NYISO
Point of Interconnection
South Ripley Substation 230kV
Data Source
LBNL