White Creek Solar
BetaActiveSolarNYISOLBNL
135 MW generation in Livingston, NY · In queue since November 2018 · Proposed COD November 2027
135 MW
Capacity
1
Components
Solar
7y 4m
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
9 years
Impact Study25%
Queue EntryNov 1, 2018
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-11-01
Project Details
State
NY
County
Livingston
Region
NYISO
Developer
White Creek Solar, LLC
Utility
RG&E
Entity
NYISO
Point of Interconnection
Sta 82 - Sta 128 115kV
Data Source
LBNL
No news available for this project.