Tracy Solar Energy Centre
BetaActiveSolarNYISOLBNL
119 MW generation in Jefferson, NY · In queue since October 2018 · Proposed COD November 2028
119 MW
Capacity
1
Components
Solar
7y 5m
In Queue
System Impact Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
10y 1m
Impact Study25%
Queue EntryOct 18, 2018
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-11-01
Project Details
State
NY
County
Jefferson
Region
NYISO
Developer
EDF Renewables Development, Inc.
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Thousand Island - Lyme 115kV
Data Source
LBNL
No news available for this project.