Sunrise Wind
880 MW generation in Suffolk, NY · In queue since September 2018 · Proposed COD March 2026
880 MW
Capacity
1
Components
Offshore Wind
7y 6m
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
7y 6m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-03-01
State
NY
County
Suffolk
Region
NYISO
Developer
Sunrise Wind LLC
Utility
LIPA
Entity
NYISO
Point of Interconnection
Holbrook 138kV & West Bus 138kV
Data Source
LBNL
Sunrise Wind Construction May Resume According to Most Recent Court Order
Ørsted, the parent company of the Sunrise Wind turbine project, announced today that the U.S. District Court for the District of Columbia...
Sunrise Wind Construction May Resume According to Most Recent Court Order
Ørsted, the parent company of the Sunrise Wind turbine project, announced today that the U.S. District Court for the District of Columbia...
Sunrise Wind Construction May Resume According to Most Recent Court Order
Ørsted, the parent company of the Sunrise Wind turbine project, announced today that the U.S. District Court for the District of Columbia...
Sunrise Wind Construction May Resume According to Most Recent Court Order
Ørsted, the parent company of the Sunrise Wind turbine project, announced today that the U.S. District Court for the District of Columbia...