Magruder BESS
BetaActiveBatteryNYISOLBNL
20 MW storage in Ulster, NY · In queue since July 2018 · Proposed COD January 2025
20 MW
Capacity
1
Components
Battery
7y 8m
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
6y 6m
Schedule
15 months past proposed COD
Facilities Study50%
Queue EntryJul 18, 2018
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-01-01
Project Details
State
NY
County
Ulster
Region
NYISO
Developer
Mitchell Energy Facility, LLC
Utility
CHG&E
Entity
NYISO
Point of Interconnection
East Walden - Modena 115kV
Data Source
LBNL