Empire Wind 1
816 MW generation in Kings, NY · In queue since June 2018 · Proposed COD December 2026
816 MW
Capacity
1
Components
Offshore Wind
7y 9m
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
8y 6m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
State
NY
County
Kings
Region
NYISO
Developer
Empire Offshore Wind LLC
Utility
ConEd
Entity
NYISO
Point of Interconnection
Gowanus 345kV
Data Source
LBNL
Court lifts construction ban on Equinor’s Empire Wind off New York
Construction at Equinor's (OSE:EQNR) Empire Wind 1 wind project off the New York coast will resume following a court ruling that lifted the...
Equinor Sues US Gov’t Over Empire Wind 1 Construction Halt
Equinor has filed a civil suit in the US District Court for the District of Columbia against the order that suspended construction on five...
Blown in the wind: Trump administration halts Empire Wind 1 for second time
The future of Empire Wind 1 is blowing in the wind once again after the Trump administration announced Dec. 22 that it would pause the...
Shipbuilder says Maersk wants to abandon $475 million WTIV
Maersk Offshore Wind seeks to terminate its contract for a $475 million wind turbine installation vessel that's already nearly complete and...