Ticonderoga Solar
BetaActiveSolarNYISOLBNL
20 MW generation in Essex, NY · In queue since June 2018 · Proposed COD March 2025
20 MW
Capacity
1
Components
Solar
7y 9m
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
6y 9m
Schedule
13 months past proposed COD
Facilities Study50%
Queue EntryJun 12, 2018
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-03-01
Project Details
State
NY
County
Essex
Region
NYISO
Developer
ELP Ticonderoga Solar LLC
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Ticonderoga 115kV - Republic Line 2
Data Source
LBNL