Moraine Solar Energy Center
BetaActiveSolarNYISOLBNL
93.5 MW generation in Allegany, NY · In queue since June 2018 · Proposed COD October 2027
93.5 MW
Capacity
1
Components
Solar
7y 9m
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
9y 4m
Impact Study25%
Queue EntryJun 4, 2018
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-10-01
Project Details
State
NY
County
Allegany
Region
NYISO
Developer
EDF Renewables Development, Inc.
Utility
NYSEG
Entity
NYISO
Point of Interconnection
Moraine 115kV
Data Source
LBNL
No news available for this project.