Bear Ridge Solar
BetaActiveSolarNYISOLBNL
100 MW generation in Niagara, NY · In queue since March 2018 · Proposed COD April 2027
100 MW
Capacity
1
Components
Solar
8 years
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
9y 1m
Impact Study25%
Queue EntryMar 20, 2018
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-04-01
Project Details
State
NY
County
Niagara
Region
NYISO
Developer
Bear Ridge Solar, LLC
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Mountain- Lockport 115kV
Data Source
LBNL
No news available for this project.