Watkins Glen Solar
BetaActiveSolarNYISOLBNL
50 MW generation in Schuyler, NY · In queue since March 2017 · Proposed COD January 2025
50 MW
Capacity
1
Components
Solar
9 years
In Queue
System Impact Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
7y 10m
Schedule
15 months past proposed COD
Impact Study25%
Queue EntryMar 27, 2017
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-01-01
Project Details
State
NY
County
Schuyler
Region
NYISO
Developer
Watkins Glen Solar Energy Center, LLC
Utility
NYSEG
Entity
NYISO
Point of Interconnection
Bath - Montour Falls 115kV
Data Source
LBNL
No news available for this project.