Alle Catt II Wind
BetaActiveWindNYISOLBNL
339.1 MW generation in Cattaraugus, NY · In queue since January 2017 · Proposed COD December 2026
339.1 MW
Capacity
1
Components
Wind
9y 2m
In Queue
System Impact Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
9y 11m
Impact Study25%
Queue EntryJan 4, 2017
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-01
Project Details
State
NY
County
Cattaraugus
Region
NYISO
Developer
Alle-Catt Wind Energy LLC
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Stolle Rd - Five Mile Rd 345kV
Data Source
LBNL