Niagara Solar — Project Summary

Queue ID
NYISO-592
Capacity
20 MW
Technology
Solar
Status
active
Location
Wyoming, NY
Region
NYISO
Developer
Niagara NY Solar LLC
IA Status
Facility Study

Niagara Solar

BetaActiveSolarNYISOLBNL

20 MW generation in Wyoming, NY · In queue since December 2016 · Proposed COD December 2026

20 MW

Capacity

1

Components

Solar

9y 3m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

10 years

Facilities Study50%
Queue EntryDec 2, 2016

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-01

Project Details

State

NY

County

Wyoming

Region

NYISO

Developer

Niagara NY Solar LLC

Utility

NYSEG

Entity

NYISO

Point of Interconnection

Bennington 34.5kV

Data Source

LBNL