Niagara Solar
BetaActiveSolarNYISOLBNL
20 MW generation in Wyoming, NY · In queue since December 2016 · Proposed COD December 2026
20 MW
Capacity
1
Components
Solar
9y 3m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
10 years
Facilities Study50%
Queue EntryDec 2, 2016
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-01
Project Details
State
NY
County
Wyoming
Region
NYISO
Developer
Niagara NY Solar LLC
Utility
NYSEG
Entity
NYISO
Point of Interconnection
Bennington 34.5kV
Data Source
LBNL