Scipio Solar
BetaActiveSolarNYISOLBNL
18 MW generation in Cayuga, NY · In queue since December 2016 · Proposed COD December 2024
18 MW
Capacity
1
Components
Solar
9y 3m
In Queue
Facility Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
8 years
Schedule
16 months past proposed COD
Facilities Study50%
Queue EntryDec 2, 2016
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-01
Project Details
State
NY
County
Cayuga
Region
NYISO
Developer
SunEast Scipio Solar LLC.
Utility
NYSEG
Entity
NYISO
Point of Interconnection
Scipio 34.5kV
Data Source
LBNL
No news available for this project.