Watkins Rd Solar
BetaActiveSolarNYISOLBNL
20 MW generation in Herkimer, NY · In queue since November 2016 · Proposed COD July 2026
20 MW
Capacity
1
Components
Solar
9y 4m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
9y 8m
Facilities Study50%
Queue EntryNov 8, 2016
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-07-01
Project Details
State
NY
County
Herkimer
Region
NYISO
Developer
SunEast Watkins Road Solar LLC
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Watkins Rd - Ilion 115kV
Data Source
LBNL