Watkins Rd Solar — Project Summary

Queue ID
NYISO-586
Capacity
20 MW
Technology
Solar
Status
active
Location
Herkimer, NY
Region
NYISO
Developer
SunEast Watkins Road Solar LLC
IA Status
Facility Study

Watkins Rd Solar

BetaActiveSolarNYISOLBNL

20 MW generation in Herkimer, NY · In queue since November 2016 · Proposed COD July 2026

20 MW

Capacity

1

Components

Solar

9y 4m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

9y 8m

Facilities Study50%
Queue EntryNov 8, 2016

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-07-01

Project Details

State

NY

County

Herkimer

Region

NYISO

Developer

SunEast Watkins Road Solar LLC

Utility

NM-NG

Entity

NYISO

Point of Interconnection

Watkins Rd - Ilion 115kV

Data Source

LBNL

No news available for this project.