Dog Corners Solar
BetaActiveSolarNYISOLBNL
20 MW generation in Cayuga, NY · In queue since November 2016 · Proposed COD April 2026
20 MW
Capacity
1
Components
Solar
9y 4m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
9y 5m
Facilities Study50%
Queue EntryNov 2, 2016
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-04-01
Project Details
State
NY
County
Cayuga
Region
NYISO
Developer
SunEast Dog Corners Solar LLC
Utility
NYSEG
Entity
NYISO
Point of Interconnection
Aurora 34.5kV
Data Source
LBNL
No news available for this project.