Little Pond Solar
BetaActiveSolarNYISOLBNL
20 MW generation in Orange, NY · In queue since September 2016 · Proposed COD January 2025
20 MW
Capacity
1
Components
Solar
9y 6m
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
8y 4m
Schedule
15 months past proposed COD
Facilities Study50%
Queue EntrySep 16, 2016
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-01-01
Project Details
State
NY
County
Orange
Region
NYISO
Developer
Little Pond Solar, LLC
Utility
O&R
Entity
NYISO
Point of Interconnection
Mongaup - Shoemaker 69kV
Data Source
LBNL
No news available for this project.